Street Repairs and Resealing

Posted on: April 28th, 2019

During May we will be repairing and refreshing the south mesa center island at the entrance on Paseo De Las Flores. This project will last approximately one week.  Please follow all signage and flagman instructions.

In June asphalt repairs will be made on many streets throughout the community.  Please slow down and follow all construction routing signs.

Beginning the week of July 8, all streets will receive an asphalt sealcoating. Work will be done Monday through Friday and is estimated to take three weeks.  This process will protect the quality condition of our streets, decrease road noise and improve the appearance of the asphalt.  A detailed plan has been developed by the construction company and will involve some street closures for a period of 24 hours.  Significant attention is being focused on traffic and parking requirements.  More information will be available and shared with everyone before the project begins.