The current schedule for the fence painting and repair project is shown below. Note that the schedule is subject to change due to various factors including weather and staffing.
As indicated previously, all materials must be removed from the fence prior to the start of the work. The Community Association maintains the exterior of all perimeter walls, pilasters or fences bordering Community Common Areas and designated in the Supplementary Declaration. Owners cannot deny or delay Community Association access to these perimeter walls over the Owner’s Lot to perform any required maintenance.
Owners shall not hang or attach any item (especially combustible materials) on or over any perimeter walls, pilasters or fences or Community Association fences or walls.
If a home is found to have materials on the fence when painting starts then any plant materials will be removed by the association and the owner will be billed for the labor involved for removal. Other materials found attached or hanging on the fence may result in a board hearing with potential fines.
SCHEDULE (as of 12/11/19)
- Lauren Court and Ranch Road are complete except for several areas to be repaired
- Ravean Court and Dylan Way should be completed by Friday, December 13th except for some repair work
- Start date of 12/16/19 for Alexandra Lane and Hampton Court
- Start date of 12/19/19 for Jensen Court, Paseo de las Flores and Lynwood Drive
- Start date of 2/3/20 for Rihely Place
- Start date of 2/10/20 for Spanish Bay and Cypress Hills Drive
- Start date of 2/17/20 for Shasta Drive and Spyglass Court
- Start date of 2/24/20 for Heritage Lane and Samuel Court
- Start date of 2/28 for Paloma Court and Verbana Court
- Start date of 3/3/20 for Via Zamia
Project completion is estimated at 3/9/20