The schedule for the fence painting and repair project as of 1/2/20 is shown below. Note that the schedule is subject to change due to various factors including weather and staffing. Several weeks were lost during the holidays due to inclement weather.
SCHEDULE (as of 1/02/20)
- Lauren Court and Ranch Road are complete except for several areas to be repaired
- Ravean Court and Dylan Way are complete except for several areas to be repaired
- Alexandra Lane and Hampton Court are complete
- Start date of 1/7/20 for Jensen Court, Paseo de las Flores and Lynwood Drive (north of 687 and 690)
- Start date of 2/5/20 for Lynwood Drive (south of 687 and 690)
- Start date of 2/20/20 for Rihely Place
- Start date of 2/25/20 for Spanish Bay and Cypress Hills Drive
- Start date of 3/2/20 for Shasta Drive and Spyglass Court
- Start date of 3/9/20 for Heritage Lane and Samuel Court
- Start date of 3/13 for Paloma Court and Verbana Court
- Start date of 3/3/20 for Via Zamia
Project completion is estimated at 3/23/20
As indicated previously, all materials must be removed from the fence prior to the start of the work.
Owners shall not hang or attach any item (especially combustible materials) on or over any perimeter walls, pilasters or fences or Community Association fences or walls.
If a home is found to have materials on the fence when painting starts then any plant materials will be removed by the association and the owner will be billed for the labor involved for removal. Other materials found attached or hanging on the fence may result in a board hearing with potential fines.