The schedule for the fence painting and repair project as of 2/24/20 is shown below. Note that the schedule is subject to change due to various factors including weather and staffing. Rainy weather may cause the schedule to slip.
SCHEDULE (as of 2/24/20)
- Lauren Court and Ranch Road are complete
- Ravean Court and Dylan Way are complete
- Alexandra Lane and Hampton Court are complete
- Jensen Court, Paseo de las Flores and Lynwood Drive (north of 687 and 690) in progress and nearing completion
- Start date of 2/10/20 for Lynwood Drive (south of 687 and 690) in progress and nearing completion
- Rihely Place and Brae Mar Court are complete
- Spanish Bay and Cypress Hills Drive in progress and nearing completion
- Shasta Drive and Spyglass Court are in progress
- Heritage Lane and Samuel Court are in progress
- Start date of 3/2/20 for Paloma Court and Verbana Court
- Start date of 3/6/20 for Via Zamia
Project completion is estimated at 3/11/20
As indicated previously, all materials must be removed from the fence prior to the start of the work.
Owners shall not hang or attach any item (especially combustible materials) on or over any perimeter walls, pilasters or fences or Community Association fences or walls.
If a home is found to have materials on the fence when painting starts then any plant materials will be removed by the association and the owner will be billed for the labor involved for removal.