- Burtech Pipeline is making great progress on this project having already completed over 30% of all trenching, laying pipe, compacting and filling
- By the end of November they will have completed their work on the remainder of Paseo de las Flores then they begin work on Lynwood Drive
- Traffic will continue to be restricted on Paseo de las Flores
- Please follow the instructions given by the flagmen in the street
- Consider using Paseo de las Verdes to enter and exit the community
- Advance notice will be given to owners about construction in front of their homes
- Work is done between 8 AM and 4:30 PM on week days only.
Visit www.encinitasranch.org/recycledwater for more details