The schedule for Monday, September 11th was disrupted due to the threat of rain this afternoon. Apache Asphalt was able to complete about half of the planned schedule. The following areas will be completed on new dates shown below: The south end of Cypress Hills Drive (the even numbered houses from Paloma Court to Paseo […]
Flyers were distributed to all of the homes in the community regarding the upcoming street resealing project. There was an error with the day associated with September 21st on the flyer. It showed Friday when in fact the 21st is a Thursday. New flyers will be posted on all of the homes where their streets […]
Below is the current schedule for the resealing work. This is subject to change due to weather and other factors. Sept 11th – Lynwood Dr (odd numbered houses between Paseo de las Flores and Cascadia Lane) , Shasta Dr, Spyglass Court, Heritage Lane, Half of Cypress Hills Dr (the even numbered houses from Paloma Court […]
As mentioned previously the community is going to have all streets resealed starting on Monday, September 13th. The work is be done by Apache Asphalt who resealed the streets in 2019. The work is being paid for using a small portion of our reserves and is supported by the reserve study for 2023. It is […]
On Monday, August 14th and Tuesday, August 15th the community will have crack sealant applied to all streets. You will be seeing Apache trucks completing this work. You can drive on the crack sealant as soon as it applied. It dries immediately and will not cause damage to any vehicles. No road closures are necessary. […]
After a competitive bid analysis the community has chosen Apache Asphalt to seal cracks in the road surfaces and reseal all of the streets in Encinitas Ranch. The crack sealing will be completed on Monday, August 14th and Tuesday the 15th. This work will not interfere with traffic and vehicles can drive on any street […]