Road Resealing Project – Update Friday, September 22nd Weather Delay

Unfortunately, the weather today, Friday, September 22nd, interfered with the road resealing project. Apache Asphalt had to stop work mid-morning and will start again on Monday, the 25th. Their policy is not to do any work unless there is less than a 20% chance of rain and that was not the case today. The following […]

Read more >

City planted trees on Lot 15

Over the past few months the City of Encinitas and their Parks & Recreation Department has planted over 20 oak and torrey pine trees to Lot 15 which is the portion of one of the surrounding trails behind Lynwood Drive. These will further enhance the aesthetics of the trail. Our landscaping committee works very closely […]

Read more >

Road Resealing Project – Remaining Dates

This post is just to remind all members that Apache Asphalt still has three days remaining to complete their road resealing project. This schedule is subject to change with weather being a major factor. Sept 21th – Verbena Court, Paloma Court (south from Cascadia Lane), Samuel Court, South end of Cypress Hills Dr (odd numbered […]

Read more >

City Council approves new traffic measures for Quail Gardens Drive and Saxony Road

On Wednesday, September 13th the Encinitas City Council heard recommendations from city staff regarding plans to mitigate speeding and improve safety on Quail Gardens Drive and Saxony Road. After a year and a half of lobbying on the part of the Four Corners Consortium the council agreed with a plan to install two four way […]

Read more >

ROAD CLOSURE – PASEO DE LAS FLORES September 18th

Paseo de las Flores will be closed to all traffic on Monday, September 18th for street resealing. The closure is from the entry monument to the intersection of Paseo de las Flores and Lynwood Drive.  All vehicles will need to enter and exit using Paseo de las Verdes. Paseo de las Flores will be re-opened […]

Read more >

Road Resealing Schedule by date

Revised Plan as of 9/12/23  This schedule is subject to change. We recommend visiting our community website and under Community News to stay up to date on this project.  Sept 11th – Shasta Dr, Spyglass Court, Heritage Ln Sept 12th – Rihely Court, Spanish Bay Court, North end of Cypress Hills Dr (from Jensen Court […]